Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/impacnigeria/impacore/xpdo/om/xpdoquery.class.php on line 668
Afam Gas Receiving Facilities Project - IMPaC Nigeria | Obijackson Group

Afam Gas Receiving Facilities Project

For the Afam GRF Greenfield fast track project IMPaC provided integrated project development expertise and has significantly contributed to the first gas delivery in December 2005, as planned. The facilities include :

  • 2 inlet HP separators, water bath heater for optional superheating,
  • 2 filters in series for solid removal (> 5 microns),
  • condensate storage tank (30 m³),
  • open drain system incl. coalescer for oil removal,
  • flare stack with integrated KO-drum,
  • truck loading facility for condensate export.

Scope of Work

  • Project management
  • Review / amendment of Shell FEED
  • Basic & detailed design “fit for air freighting”
  • Procurement assistance
  • Site support
  • Commissioning & start-up assistance

IMPaC‘s Services

  • 12,000 hours