Brownfield Revamp Project at 1CPF and 4Flowstations
(NBNK, SBNK, YOKRI & ESTUARY)

  • Two train screw compressors (2x100%),
  • One single train JT – LTS unit , HC dew pointing to ELPS pipeline export specification.
  • Tie-in of a new NAG well via a new Slug Catcher.
  • Rerouting HP condensate from the existing TEG contactor, the new LTS unit, the new slug catcher, the new compressor KO vessels and existing export compressor KO vessel via a new condensate header to the existing estuary slug catcher.
  • Two reciprocating export compressors (2x50% Capacity) which will compress the gas from the new JT – LTS unit discharge pressure to the operating pressure of the ELPS pipeline at the tie-in point.
  • A bypass arrangement - export gas from the OGGS line to ELPS line if the CPF is not available.
  • Fiscal metering facility for the ELPS gas export line.
  • Rerouting the seal gas supply for the CPF export compressors to a dry gas source.
  • Yokri flow station gas gathering.
  • Decommissioning of Yokri gas lift compression facilities.

Scope of Work:

  • FEED
  • Detail Engineering Design (DED)
  • Design Reviews and Safety Studies
  • Follow-on Engineering

IMPaC’s Service:

  • 40,000 – 45,000 hours approx (ongoing)